HLG Contracting

  • Duhail-Res-1
  • New Al Kaaban RPS-01
  • Location : Qatar
  • Contract Value US$ : 19 Million
  • Client : Qatar General Electricity & Water Corporation (KAHRAMAA)
  • Commencement : 2012

HLG is responsible for the construction of a Reservoir and Pumping Station (RPS) at Al Kaaban, along with Associated Pipelines.

The project involves a design and construction contract consisting of the following works:

  • A geotechnical investigation
  • A hydraulic study for the new Al Kaaban water supply, storing and distribution system including surge and transient analysis for the complete piping system
  • One new reinforced concrete reservoir with a six million gallon capacity
  • A new pumping station to accommodate six VFD pumps including controls, instrumentation and MEP works
  • A concrete boundary wall around the new and future reservoirs
  • A new tanker filler station
  • A new guard house and 11KV substationA new accommodation building
  • A new chlorination building and systemInlet and outlet pipe works and valve chambers
  • Road works, street lighting and landscaping